A professional Ringlock structure is not created simply by connecting individual components together. Although modular systems are designed for fast assembly, the quality and safety of the final structure depend heavily on the installation sequence and engineering logic behind the assembly process.
Two installation teams may use the same Ringlock components, the same drawings, and similar equipment, yet achieve completely different results. The difference is often not the material or the hardware—it is the methodology used during construction.
A temporary structure must not only be stable after completion. It must remain stable throughout every stage of installation.
This is the fundamental principle behind professional Ringlock installation:
Foundation First.
Vertical Second.
Bracing Always.
These three principles establish the structural foundation for controlling alignment, transferring loads, and maintaining temporary stability during the entire erection process.
For a complete understanding of modular temporary structures, this methodology should be considered together with the broader principles explained in Dragon Stage Installation Principles for Temporary Structures and the engineering logic behind Modular System Logic for Stage, Truss & Scaffold Systems.
In temporary event construction, installation speed is important. Events often have strict schedules, limited access time, and narrow installation windows.
However, speed should never become the primary objective.
A Ringlock structure is a progressive load-bearing system. During installation, the structure changes continuously:
Individual components become connected members.
Separate frames become a three-dimensional structure.
Temporary instability gradually develops into final structural stability.
Every installation step influences the next one.
A small error at the beginning can become a significant structural problem later.
For example:
An uneven foundation can create vertical alignment problems.
↓
Vertical alignment problems can affect beam connections.
↓
Connection errors can influence roof geometry.
↓
Roof deformation can affect fabric tension and wind resistance.
This means that installation is not simply a process of assembling parts. It is a controlled process of building a reliable load path.
A professional installation sequence follows the same logic as structural design:
Where does the load start?
How does the load transfer?
How is movement controlled?
This principle applies not only to Ringlock structures but also to other modular event systems, including Event Truss Systems, Roof Truss Systems, and temporary stage structures.
The first and most important stage of Ringlock installation is not the vertical frame.
It is the foundation.
Before any standards, ledgers, or braces are installed, the installation team must establish a stable and accurate base condition.
A Ringlock structure transfers vertical loads from the upper structure down to the ground through a continuous load path:
Roof / Platform Load
↓
Horizontal Members
↓
Vertical Standards
↓
Base Jacks
↓
Ground Support
If the foundation condition is incorrect, every component above will inherit the error.
A simple principle applies:
A Ringlock structure can never become more accurate than its foundation.
Before installation begins, the site should be evaluated for:
Uneven ground can create different starting elevations between standards.
This may lead to:
Unequal loading between columns
Difficult connection alignment
Additional stress on horizontal members
Problems during roof installation
The ground must be capable of supporting the expected loads.
Temporary event structures may experience:
Dead load from the structure itself
Equipment loads
Audience loads
Wind loads
Dynamic loads during operation
A visually flat surface does not always mean the ground has sufficient bearing capacity.
Outdoor temporary structures must consider water accumulation.
Poor drainage may cause:
Ground settlement
Base movement
Uneven loading
Reduced long-term stability
For projects involving complex temporary structures, load transfer analysis should be considered during the design stage. More information about structural load evaluation can be found in Load Analysis for Modular Stage Systems.
After the site condition has been confirmed, the installation team establishes the base grid.
This step determines:
Structure dimensions
Column positions
Alignment accuracy
Connection locations
The base grid should be checked before vertical standards are installed.
A common mistake is trying to correct positioning problems after several levels have already been assembled.
At that stage, adjustments become more difficult because the error has already transferred upward through the structure.
Professional installers therefore follow a simple rule:
Measure first.
Install second.
Expand third.
Base jacks provide adjustment between the ground condition and the Ringlock structure.
They allow installers to:
Compensate for minor elevation differences
Establish a consistent starting height
Improve structural alignment
However, base jacks are adjustment components—not solutions for poor foundations.
They cannot replace:
Proper ground preparation
Stable bearing conditions
Correct layout measurement
The purpose of adjustment is to refine accuracy, not compensate for incorrect installation planning.
After the foundation has been prepared, the next priority is vertical alignment.
Many installation problems occur because workers focus on expanding the structure before establishing accurate vertical references.
A Ringlock structure should first create a stable and accurate structural frame.
The vertical standards are the primary load-carrying members. They determine:
Overall height
Column alignment
Load distribution
Connection accuracy
Final structural geometry
If the vertical system is inaccurate, every additional component will follow the same error.
A small deviation at the bottom of a structure can become larger as the structure increases in height.
For example:
A small inclination in one standard may cause:
Difficulty connecting upper ledgers
Uneven roof support
Misaligned panels or platforms
Additional bending forces
The purpose of vertical control is not only appearance.
It directly affects structural behavior.
A properly aligned vertical system allows loads to transfer mainly through axial compression, which is the condition modular structures are designed to achieve.
Poor alignment can introduce unwanted bending forces and reduce structural efficiency.
Experienced installation teams normally complete and verify the first structural bay before expanding the entire structure.
The first bay establishes the reference for:
Horizontal alignment
Vertical alignment
Connection accuracy
Bracing position
Once the first bay is confirmed, the following sections can be expanded based on a verified reference.
This approach is slower during the first few minutes but significantly reduces correction work later.
It follows the engineering principle:
Accuracy at the beginning creates efficiency throughout the entire installation process.
Among all Ringlock installation principles, bracing is one of the most frequently misunderstood elements.
Many inexperienced installers consider braces as secondary components that are added after the main frame has been completed. However, from an engineering perspective, bracing is not an optional reinforcement element.
It is a fundamental part of the structural system.
A Ringlock structure without sufficient bracing may have vertical members and horizontal members connected correctly, but it does not yet have adequate resistance against lateral movement.
The difference is:
Without bracing:
Individual frames exist.
↓
With bracing:
The frames become a stable three-dimensional structure.
This is why professional installers follow the principle:
Bracing Always.
Bracing must be considered throughout the installation process, not as a final adjustment.
For a deeper understanding of how bracing transfers structural forces, see What Is Truss Bracing and How Does It Transfer Structural Loads? and What Is a Truss Brace and How Does It Improve Stability?.
A common misunderstanding is:
"The structure will become stable after everything is installed."
This is only partially correct.
The final completed structure may have sufficient stability, but the installation process itself creates temporary conditions where the structure is more vulnerable.
During construction, the system may experience:
Incomplete frames
Uneven temporary loading
Wind pressure
Worker movement
Equipment impact
Temporary lifting forces
At these stages, the structure does not yet have its final stiffness.
Bracing provides temporary stability while the structure is being transformed from individual components into a complete load-bearing system.
This concept is especially important for temporary structures because, unlike permanent buildings, the installation process itself is part of the structural lifecycle.
A professional installation methodology considers two different structural conditions.
This refers to the completed structure after:
All standards are installed
All ledgers are connected
All braces are fixed
Roof systems are completed
Loads are applied according to design requirements
This refers to every intermediate stage during construction.
For example:
First level completed
Second level partially installed
Roof supports being assembled
Fabric being tensioned
A structure that is stable after completion does not automatically mean it was safe during installation.
This distinction is one of the most important differences between professional engineering installation and simple component assembly.
The main purpose of bracing is to control lateral movement and improve structural stiffness.
A modular Ringlock system mainly transfers vertical loads through standards.
However, temporary structures are also affected by horizontal forces, including:
Wind loads
Equipment movement
Dynamic event loads
Accidental impact
Installation forces
Without adequate bracing, lateral forces can cause:
Frame deformation
Connection movement
Progressive instability
Excessive stress concentration
Bracing creates additional load paths that allow horizontal forces to be transferred safely through the structure.
The basic load path becomes:
Horizontal Force
↓
Bracing Members
↓
Ringlock Connections
↓
Vertical Standards
↓
Foundation
This is why bracing is not simply about making the structure stronger.
It is about controlling how forces move through the structure.
Another important methodology principle is:
Symmetry Before Expansion.
A common installation mistake is expanding the structure in one direction too quickly.
For example:
Completing one side first
Adding multiple levels before balancing the opposite side
Installing roof components before the main frame is symmetrical
Although this may appear faster, it can create uneven temporary loading.
A modular structure works best when it develops evenly.
Professional installation normally follows:
Establish the first reference bay.
Confirm alignment.
Expand in a controlled sequence.
Maintain balanced development on all sides.
This reduces:
Temporary twisting
Uneven loading
Connection stress
Alignment correction work
The objective is not simply to build faster.
The objective is to maintain a predictable structural condition throughout construction.
Large Ringlock structures are usually composed of repeated structural bays.
A bay includes:
Vertical standards
Horizontal ledgers
Bracing members
Connections
A common mistake is installing scattered components throughout the site without completing a stable reference section.
A better approach is:
Complete one structural bay.
↓
Check alignment.
↓
Verify connections.
↓
Continue expansion.
This creates a controlled installation rhythm.
Each completed bay becomes a verified reference for the next section.
The benefits include:
Faster correction
Easier inspection
Reduced cumulative errors
Better quality control
This principle is widely applicable to modular temporary systems, including Modular System Logic for Stage, Truss & Scaffold Systems.
Roof systems are often installed near the final stage because they introduce additional loads and environmental effects.
A roof structure adds:
Additional dead load
Wind exposure
Fabric tension forces
Larger surface area
Installing roof components too early can create unnecessary risks.
The correct sequence is:
Foundation
↓
Vertical Structure
↓
Horizontal Members
↓
Bracing
↓
Roof Support
↓
Roof Fabric
↓
Final Tensioning
This sequence ensures the supporting structure has already achieved sufficient stability before additional loads are introduced.
For temporary roof structures and related engineering considerations, refer to Roof Truss Systems and How to Assemble Aluminum Event Stage Roof Truss.
The roof fabric is not simply a cover.
It is part of the operational performance of the temporary structure.
Correct tension improves:
Water drainage
Appearance
Wind performance
Fabric lifespan
However, tensioning should only happen after the supporting structure has reached the correct geometry.
If fabric is tensioned before the frame is properly aligned, it may:
Pull the structure out of position
Create uneven forces
Increase stress on connection points
Produce long-term fabric damage
Therefore:
Structure first. Geometry second. Tension last.
This principle is also discussed in practical installation guidance such as How Are Steel Ringlock Trusses Installed and What Safety Considerations Must Be Taken Into Account?.
The complete Ringlock installation methodology can be understood as the gradual creation of a reliable load path.
The sequence is not accidental.
It follows structural logic:
Foundation
↓
Provides stable support
↓
Vertical Standards
↓
Create primary compression paths
↓
Horizontal Members
↓
Connect the structural grid
↓
Bracing
↓
Controls lateral movement
↓
Roof System
↓
Introduces additional loads
↓
Tensioning
↓
Optimizes final performance
At every stage, the installer is not simply adding components.
The installer is creating a controlled structural system.
This is the difference between assembling a Ringlock structure and engineering one.
A professional Ringlock installation methodology exists because many structural problems do not come from incorrect components, but from incorrect installation sequences.
The same Ringlock standards, ledgers, braces, and connections can produce very different results depending on how they are assembled.
The following mistakes are commonly observed when installers focus only on speed or component connection while ignoring structural behavior.
One of the most common mistakes is beginning installation before properly checking the foundation condition.
Some teams assume that because the Ringlock system has adjustable base jacks, ground preparation is less important.
This is incorrect.
Base adjustment can compensate for small differences in elevation, but it cannot correct:
Poor soil bearing capacity
Excessive settlement
Incorrect structural positioning
Severe ground slope
Water accumulation problems
When the foundation condition is inaccurate, the entire structure inherits the error.
Typical consequences include:
Misaligned vertical standards
Difficult connection installation
Uneven load distribution
Roof deformation
Additional stress on connections
The foundation is not simply the place where the structure stands.
It is the beginning of the entire load transfer system.
For more information about modular structural stability and load transfer, see Load Analysis for Modular Stage Systems.
Another common mistake is expanding horizontally or vertically before confirming the accuracy of the initial frame.
During installation, workers may focus on completing more sections quickly, but small alignment errors can accumulate as the structure becomes larger.
A small deviation at the lower level may result in:
Misaligned upper connections
Difficulty installing roof structures
Uneven platform levels
Increased bending forces
Professional installers establish a reference system first.
This includes checking:
Vertical alignment
Horizontal level
Grid dimensions
Connection positioning
Only after the first structural section is verified should expansion continue.
This principle is also applicable to other modular systems, including Installation Methodology for Modular Stage, Truss and Scaffold Systems.
One of the most dangerous misconceptions is installing all main members first and adding braces afterward.
Although this may appear efficient, it creates a period where the structure has limited resistance against lateral movement.
Without proper bracing, the structure may be vulnerable to:
Wind forces
Temporary loading
Accidental impact
Installation movement
Bracing should be installed as the structure develops.
It is not a decorative reinforcement.
It is a structural stability system.
For further understanding of structural bracing principles, refer to:
Roof installation is often considered the final visual stage of construction, but from an engineering perspective it is a major structural transition.
Adding roof components introduces:
Additional dead load
Larger wind-exposed surfaces
Fabric tension forces
Additional connection forces
Installing roofing before the supporting structure is fully stabilized may create unexpected stress conditions.
A safer sequence is:
Foundation
↓
Vertical structure
↓
Horizontal members
↓
Bracing
↓
Roof support
↓
Roof fabric
↓
Tension adjustment
This sequence ensures that the structure is prepared before accepting additional loads.
For roof system engineering considerations, see Roof Truss Systems.
Roof fabric tension is an important part of temporary structure performance.
However, tensioning should happen only after:
The frame is aligned
Connections are secured
Roof geometry is confirmed
Incorrect tensioning may cause:
Uneven roof shape
Poor drainage
Excessive stress at attachment points
Premature fabric damage
A professional approach is:
Confirm structure geometry.
Install fabric correctly.
Apply tension gradually and symmetrically.
Perform final inspection.
The goal is balanced tension, not maximum tension.
A completed Ringlock structure may be designed to resist environmental loads, but the partially completed structure during installation can be much more vulnerable.
Strong wind conditions are especially dangerous when:
Roof beams are being lifted
Large fabric sections are being installed
Sidewalls are exposed
Bracing is incomplete
Weather monitoring should be part of the installation plan.
Installation should be suspended when conditions exceed safe working limits.
Safety is not only about the final structure.
Safety begins from the first component installed.
For operational safety considerations, see What Should Be Paid Attention to When Using Event Truss?.
Before considering a Ringlock installation complete, professional teams should verify the following:
✓ Ground condition evaluated
✓ Base positions measured
✓ Bearing condition confirmed
✓ Base adjustment completed
✓ Standards installed according to layout
✓ Vertical alignment checked
✓ Connection positions verified
✓ First structural bay inspected before expansion
✓ All required diagonal braces installed
✓ Brace connections fully secured
✓ Temporary stability maintained during construction
✓ No unauthorized brace removal
✓ Supporting frame completed before roof installation
✓ Roof members correctly connected
✓ Fabric installed without twisting
✓ Tension applied evenly
✓ Structural alignment confirmed
✓ Connections checked
✓ Loose components removed
✓ Weather conditions reviewed
✓ Final configuration matches approved design
The purpose of a professional installation methodology is not simply to make installation faster.
It is to make the installation process predictable.
A temporary structure experiences many different conditions before it reaches its final form. During this process, every component added or adjusted changes the way forces move through the system.
The principle:
Foundation First.
Vertical Second.
Bracing Always.
represents a simple but powerful engineering approach:
Establish reliable support.
Create accurate structural geometry.
Maintain stability throughout construction.
A successful Ringlock installation is not achieved when the last component is connected.
It is achieved when every stage of construction has maintained structural control.
Because all structural loads eventually transfer to the ground. An inaccurate or unstable foundation affects alignment, load distribution, and overall structural performance.
Because early alignment errors accumulate as the structure grows. Establishing an accurate reference frame reduces correction work and improves structural reliability.
Because the structure requires temporary stability before it reaches its final configuration. Bracing controls lateral movement throughout the installation process.
It is not recommended. Roof fabric introduces additional forces and should only be tensioned after the supporting structure has achieved correct geometry and stability.
Yes. The same components can perform differently depending on installation quality, connection accuracy, and structural sequence control.
No. The principles of foundation control, vertical alignment, bracing, and progressive stabilization also apply to many temporary structures, including stage systems, roof structures, truss systems, and modular scaffolding.
To further understand temporary structure engineering and Ringlock applications, explore:
Dragon Stage Installation Principles for Temporary Structures
What Is a Steel Ringlock Structure? Applications, Advantages and Event Uses
How Are Steel Ringlock Trusses Installed and What Safety Considerations Must Be Taken Into Account?
How Are Steel Ringlock Structures Manufactured for Event Applications?
DragonStage 10×10m (32.8×32.8ft) aluminum modular event stage platform, assembled from 50 wooden-topped 2×1m stage decks with a braced support structure and two access staircases.
Available in three adjustable height ranges: 0.4–0.8m, 0.8–1.2m and 1.2–2.0m.
The standard component schedule includes 115 stage braces, 66 extendable support stands, 66 adjustable bases and two wooden-topped three-step staircases. The stair configuration must be matched to the selected platform height.
Dragonstage custom 4m wide × 4m deep × 3m high FOH (Front of House) control booth for concerts, festivals and professional event production.
The proposed structure combines a modular support framework, a single-sloped roof, three PVC curtain walls and an open front for sound, lighting and technical control operations.
Designed to provide a defined 16m² nominal control area, this temporary FOH shelter can be customized according to equipment layout, platform requirements and site conditions.
DragonStage custom 16m (52.5ft) diameter circular modular stage with a recommended height of 1.2m (3.94ft), designed for concerts, Christmas celebrations, choir performances and large indoor events.
The proposed configuration includes curved perimeter guardrails, decorative stage skirting, one wide front staircase, two rear access staircases and staircase handrails.
Designed around a 19-performer musical arrangement, the stage layout can be adjusted according to the final instrument requirements.
DragonStage spigot-connected aluminum triangular circular truss, available in six nominal diameters: 3m, 4m, 5m, 6m, 8m and 10m (9.84–32.81ft).
Manufactured from curved triangular truss sections, each complete ring uses a conical spigot connection system with matching connectors, pins and safety clips.
Designed for professional stage lighting, concert productions, exhibitions, DJ events and custom circular lighting installations. Truss profile dimensions, section quantities and structural load ratings are determined according to the selected configuration.
DragonStage aluminum triangular circular truss with bolted connections, available in six nominal diameters: 3m, 4m, 5m, 6m, 8m and 10m (approximately 9.84–32.81ft).
Manufactured from curved triangular truss sections that assemble into a complete circular ring, this product is suitable for consideration in stage lighting, exhibition displays, DJ installations and custom event structures.
The bolt-connected design distinguishes this model from spigot-connected circular truss systems. Truss profile dimensions, tube specifications, segment quantities and allowable loads are confirmed according to the selected diameter and project requirements.
16x10x8m Aluminum A-Frame Concert Roof Truss with 2m Side Wings and Stage
DragonStage PT34-C21-R aluminum box truss corner featuring a smooth, rounded 90-degree shape and two connection directions.
This compact corner component uses 50×2mm main tubes, has a nominal size of 0.5m (1.64ft), and weighs approximately 4.4kg (9.71lb).
Designed for compatible PT34 modular lighting truss assemblies, exhibition frameworks, DJ installations and event truss systems where a rounded corner appearance is preferred over a conventional sharp-angle connector.
8×8×4m Outdoor Concert Lighting Truss System with Ground Support Towers
DragonStage 8×8×4m (26.2×26.2×13.1ft) modular aluminum lighting truss system for outdoor concerts, live events, festivals and temporary stage lighting installations.
Designed as a square-format ground support lighting structure, this system can incorporate horizontal aluminum box trusses, vertical towers, lifting components and compatible stage lighting equipment.
A related DragonStage configuration lists CS289×289mm aluminum truss with 50×3mm main tubes and a four-tower lifting arrangement. Exact component quantities, equipment supply scope and structural ratings must be confirmed for this product before ordering.
5.8m Crank-Up Speaker Stand for Event Sound Systems
DragonStage 5.8m (19ft) crank-up speaker stand for professional event sound system applications, including portable PA equipment, stage audio setups and compatible speaker lifting arrangements.
Designed for customers requiring adjustable speaker positioning above ground level, this equipment must be selected according to the actual speaker weight, mounting interface, supporting surface and verified operating limits.
The original product is listed as a 5.8m speaker crank stand. Detailed lifting capacity, self-weight, mounting specifications and packing dimensions must be confirmed for this exact model before ordering.
6.5m Heavy-Duty Steel Crank-Up Lighting Stand – A1, 250kg Capacity
DragonStage A1 heavy-duty steel crank-up lighting stand with a maximum height of 6.5m (21.3ft) and a manufacturer-listed loading capacity of 250kg (551lb).
Designed for compatible stage lighting and truss lifting arrangements, this professional event stand has a listed self-weight of 100kg and a packing weight of 110kg. Suitable for consideration in indoor events, stage productions and rental equipment systems when the complete loading and support configuration is verified.
4m Manual Winch Crank-Up Lighting Stand – A2, 50kg Capacity
DragonStage A2 manual crank-up lighting stand with a handy winch, adjustable from 1.6m to 4m (5.25–13.12ft) and rated at 50kg according to the original manufacturer specification.
Designed for compatible portable lighting applications, mobile DJs and small event setups, this stand provides mechanical height adjustment without requiring an electric lifting motor. The original product lists a packed size of 2.02×0.24×0.19m and a weight of approximately 19.2–20kg, subject to final packing confirmation.
DragonStage HD-013 adjustable low crank-up lighting stand for DJs, small events, mobile entertainment and temporary stage lighting applications.
This compact tripod features a 60kg manufacturer-listed load capacity, a 1.5m T-bar with a 35×35mm square-tube profile, a 1.3m nominal base dimension and a 14kg net weight. The original specification lists a lifting height of 1.8–3m, although the existing product title states 1.8–4m. The actual maximum height must be confirmed before ordering.
DragonStage 12×12×6m modular aluminum A-frame roof truss system with two 2m-wide speaker wings, six main lifting towers and a PVC roof canopy. The configuration combines CS389×389mm main beams, CS289×289mm tower and roof trusses, CL30 ladder trusses, sleeve blocks, manual hoists and outrigger supports. Designed for outdoor concerts, festivals and temporary event productions requiring a covered truss framework with dedicated side speaker support positions.
14×12×7m Aluminum Semi-Circular Roof Truss System for Outdoor Event Stages
DragonStage 14m wide × 12m deep × 7m high aluminum semi-circular roof truss system for concerts, festivals and temporary event-stage structures. The original component list includes 21 curved CS389×389mm truss sections with 50×3mm main tubes, four 3m straight C389 box trusses, 24 C289 ladder trusses, three 400×400mm cubes and six 500×500mm aluminum plates. Listed packing weight is 800kg with a packing volume of 12m³. Roof covering, lifting equipment and stabilization requirements must be confirmed separately.
DragonStage 7×7×4m (23×23×13ft) custom aluminum square runway lighting truss system for event lighting, fashion shows, exhibitions and professional stage productions.
Designed around a modular square truss layout, this system can be reviewed for temporary lighting installations where a defined overhead framework is required. The final truss profile, number of supporting columns, connection method, base arrangement and equipment loading must be confirmed according to the project.
Custom Aluminum Truss Tower Top Section with 4 Black POM Wheels – Hoist System Component
DragonStage custom aluminum top section featuring four black POM (polyoxymethylene) wheels for professional event truss tower hoist systems. Designed as an upper tower component for compatible lifting arrangements used in concert production, lighting truss installations and modular event structures. The product is described for Global Truss applications, but the actual tower interface, wheel geometry and hoist compatibility must be confirmed before ordering. Custom configurations can be reviewed according to project requirements.
Spigot Truss Tower Top Section for Electric Hoist – Plastic or Aluminum Wheels
DragonStage spigot truss tower top section designed for electric motor hoist applications in modular ground support systems. The original product specifies a base-frame arrangement for 289/290mm spigot truss pillars, with plastic or aluminum wheel options and three beam-size selections. Suitable for consideration in professional truss lifting tower assemblies, subject to verified component compatibility, pulley configuration and project-specific rigging requirements.
Plastic Truss Stacker & Spacer Clip – Truss Mounting Bracket for Storage and Transport
DragonStage plastic truss stacker, spacer clip and mounting bracket accessory for organizing compatible aluminum truss sections during storage and transportation. Designed for truss handling applications where suitable separation and positioning between truss members are required. Tube compatibility, clip dimensions, material specification and quantities must be confirmed before ordering. Not intended as a substitute for rated structural connections or overhead rigging clamps.
3m Diameter F34 Aluminum Circular Lighting Truss – 4×90° Ring Package
DragonStage 3m diameter F34 aluminum circular truss package, assembled from four 90° curved square truss sections. Each section features a CS289×289mm box truss profile with 50×3mm main tubes. Connecting hardware is included according to the original product specification. Designed for event lighting, exhibitions, stage decoration and custom circular truss installations. Final diameter reference, connector type, mounting arrangement and allowable loads must be confirmed for the intended application.
DragonStage 390×390mm aluminum circular spigot lighting truss with 50×3mm main tubes, available in nominal diameters of 1m, 2m, 4m, 6m, 8m and 12m. Options range from a one-piece 1m ring to larger multi-section circular assemblies. Designed for professional event lighting, exhibitions, stage productions and custom overhead lighting layouts. Segment counts vary by diameter; installation method, rigging points and permissible loads require project-specific verification.
3.66×2.44m Aluminum Quick Lock Portable Stage with 6 Decks, Adjustable Legs & Stairs
DragonStage 3.66×2.44m (12×8ft) modular quick-lock portable stage package assembled from six 1.22×1.22m (4×4ft) aluminum-framed stage decks with wooden tops. The original package lists 24 adjustable legs, stage leg connectors and two three-step stair units. Four adjustable stage height ranges are available: 0.2–0.3m, 0.4–0.6m, 0.6–1.0m and 1.0–1.5m. Final stair compatibility and accessories must be confirmed for the selected stage height.
16U DJ Mixer Rack Flight Case – Standard & Anti-Shock Options
DragonStage 16U DJ mixer rack flight case available in standard non-anti-shock and anti-shock versions. Designed for DJs, professional audio technicians and event rental companies requiring rack-mounted equipment storage and a mixer rack configuration in one transport case. Internal dimensions, equipment depth and the protective construction of each version should be confirmed before ordering.
16U DJ Flight Case with Mixer Rack and Two Work Tables – Non-Anti-Shock
DragonStage 16U DJ flight case with an integrated mixer rack and two work tables. This standard non-anti-shock configuration combines rack-mounted audio equipment storage and an expanded DJ working area in one transportable case. Designed for mobile DJs, sound technicians, event rental companies and professional audio setups. Mixer dimensions, rack depth, table dimensions and case hardware should be confirmed before ordering.
16U DJ Flight Case with Mixer Rack and Work Table – Standard & Anti-Shock Options
DragonStage 16U DJ flight case with an integrated mixer rack and one work table, available in standard non-anti-shock and anti-shock configurations. The listed case dimensions are 530×680×750mm for the R16U product specification. Designed for DJs, audio rental companies and event technicians who need to organize rack-mounted audio equipment and a mixer workstation within one transport case. Equipment compatibility, usable interior space and the dimensions of each protective configuration must be confirmed before ordering.
DragonStage 6×4.5m (19.7×14.8ft) suspended rectangular lighting truss package, built from 290×290mm aluminum square truss with 50×3mm main tubes. The system includes eight 1-ton electric chain hoists with 25m lifting chains, an 8-channel motor controller, 25m power cables, fiber slings, shackles and individual motor transport cases. Designed for professional studio lighting, indoor concerts, exhibitions and event rigging applications, subject to project-specific structural and suspension verification.
DragonStage 4.5m diameter aluminum circular lighting truss system made from 290×290mm square truss with 50×3mm main tubes, supplied with six 1-ton electric chain hoists, 25m lifting chains, an 8-channel motor controller, fiber slings, shackles and motor transport cases. Designed for professional indoor event lighting installations, concerts, exhibitions and suspended circular rigging applications. Final suspension loads, attachment points and overhead support requirements must be verified for each installation.
DragonStage 4m wide × 3m high aluminum finish line truss gate with a 2m deep supporting base arrangement. Built from modular 290×290mm square truss sections and cube connectors, this sports event goal post truss is designed for triathlons, running races, cycling events and temporary start/finish line signage. The structure provides a framework for event banners and sponsor branding, with final banner attachments and ground stabilization requirements to be confirmed.
DragonStage 18×8m (59.1×26.2ft) modular Ringlock stage platform with a 2m (6.56ft) height and two access stair units. Featuring a large 144m² performance surface, modular Ringlock supporting framework, adjustable base supports and stair access, this stage system is designed for concerts, festivals, cultural performances and event production companies requiring a large elevated stage.
DragonStage 18m wide × 8m deep × 8m high aluminum curved roof truss stage system featuring CS520×760 main beams, 389×389mm truss pillars and 289×289mm roof top trusses. The illustrated configuration combines an arched canopy roof, four truss towers, a modular stage platform, two front access stairways and perimeter guardrails. Designed for outdoor concerts, festivals and temporary live performance installations, with project-specific structural and ground support requirements to be confirmed.
7m Aluminum H-Frame Line Array Speaker Support Tower for Outdoor Events
9m Modular Aluminum H-Frame Speaker Support Tower with Wheels and Outriggers
DragonStage 9m modular aluminum H-frame tower with 2m-long braced H-frame sections, horizontal connecting tubes, four outriggers, adjustable bases and 6-inch casters with adjustable legs. Designed as a customizable mobile-base support tower configuration for concert sound and event production applications. Speaker suspension, tower stability and movement procedures require project-specific verification.
DragonStage 10m circular aluminum lighting truss system assembled from 12 curved truss sections, each with a 30° arc. Featuring a 389×389mm square truss cross-section, 50×3mm main tubes and spigot connection accessories, this modular ring truss is designed for church lighting layouts, worship venues, concerts, exhibitions and indoor event productions. The nominal diameter and final suspension arrangement should be confirmed for the project.
DragonStage 10m wide × 10m deep × 4m high custom outdoor aluminum truss system with a ground-supported base plate configuration. Originally presented for a French village performance application, this modular truss structure is intended for temporary cultural events, community performances, festivals and outdoor event installations. Truss sections, connection methods and ground support arrangements are selected according to the final project requirements.
packing weight: 400kg
packing volume: 4cbm
DragonStage aluminum lighting boom arm and telescopic truss mounting accessory series for stage lighting installations. Available configurations include a 50–80cm adjustable arm, a 40cm horizontal boom section, a 50cm fixed boom arm and single-hook options. Designed for compatible truss and lighting support systems where adjustable fixture positioning or additional mounting locations are required.
The DragonStage Multi-Way Aluminum Truss Box Corner Cube is a modular junction component designed to connect compatible square aluminum truss sections in multiple directions.
Available in nominal 200×200mm, 300×300mm, 400×400mm, and 520×520mm truss system sizes, the connector can be supplied in 6061-T6 or 6082-T6 aluminum alloy, with Silver and Black finish options.
The standard 300mm version is specified as a 300×300×300mm cube. Six-direction connection arrangements and customized interfaces are available subject to the selected model.
Suitable for exhibition truss frames, lighting truss systems, display structures, and customized event truss configurations.
Connection compatibility must be confirmed before ordering. Spigot and bolt-nut connection systems are not automatically interchangeable.
DragonStage 290mm 6-Way Aluminum Truss Box Junction with 50×2mm main tubes, designed as a multi-directional connection component for compatible square truss systems. The six-way configuration provides connection positions for straight extensions, corners, T-junctions, cross-junctions and three-dimensional truss layouts. Final connector compatibility and hardware requirements must be confirmed for the selected truss series.
The DragonStage F34 Aluminum Truss Lectern Top Plate is a 3mm thick aluminum diamond-plate accessory designed for compatible 290mm F34 square truss lectern and pulpit assemblies.
With an approximate unit weight of 4.5kg (10lb), this metal top provides a practical surface for documents, notes, and suitable presentation accessories.
Ideal for church pulpits, conference lecterns, exhibition podiums, and custom aluminum truss furniture. This product is the top plate only, not a complete lectern. Plate dimensions and mounting compatibility should be confirmed before ordering.
The DragonStage Heavy Duty Adjustable Truss Boom Arm Bracket features an aluminum boom-arm assembly with clamp mounting, a stated total adjustable length of 50–80cm (19.7–31.5in), and a referenced 40cm (15.75in) horizontal arm dimension.
Designed for compatible stage lighting truss installations requiring an offset fixture mounting position, this model is available in Silver and Black finishes.
The original specification lists a 200kg loading figure. Its applicable extension length, mounting orientation, supporting truss conditions, and working load limit must be verified before use.
The DragonStage 50–80cm Adjustable Aluminum Truss Boom Arm is designed to provide an offset mounting position for stage lighting and compatible AV equipment on truss structures.
Featuring an adjustable aluminum boom-arm arrangement and clamp-style mounting hardware, it is available in Silver and Black finishes.
Suitable for stage lighting rigs, event truss systems, theaters, exhibitions, and temporary lighting installations. Clamp compatibility, permissible cantilever loading, and the exact adjustment geometry must be confirmed for the intended application.
DragonStage 40×40ft (12.2×12.2m) modular aluminum stage package with adjustable height from 0.6m to 1m. The system includes 50 aluminum-framed stage decks with 18mm anti-slip plywood surfaces, diagonal braces, adjustable supports, perimeter guardrail components and two 4-step access stairs. Designed for concerts, public performances, community events and rental companies requiring a large elevated stage with an integrated access and guardrail configuration.
DragonStage 40×40ft (12.2×12.2m) modular aluminum concert stage with a nominal 1m platform height, 50 plywood-surface stage decks, diagonal brace-supported framework, adjustable bases and two 4-step access stairs. Designed for concerts, festivals, public performances and event rental applications requiring a large elevated stage.
FOSHAN DRAGON STAGE
No.7,Xiaxi Industrial Area,Heshun,Nanhai District,Foshan,528241,Guangdong,China.
+86 136 3132 8997